Unfinished business: Australia's housing pipeline is not what the approvals suggest - latest building and construction news - API Magazine

Australian Property Investor (API) •
November 20, 2026 • 01:08 AM
• By <a href="/experts/newmark/niall-mcsweeney" title="View all articles from Niall McSweeney">Niall McSweeney</a>
7
7 reads 0 reactions

Unfinished business: Australia's housing pipeline is not what the approvals suggest Approvals and commencements are climbing, but completions are falling behind.

1 / 2
Swipe Photos

Approvals and commencements are climbing, but completions are falling behind.

Australia’s housing numbers look healthier than they feel. In June, 18,328 dwellings were approved, up 8.9 per cent on a year earlier. Commencements are also climbing, with 51,009 dwellings started in the March quarter, up 11.7 per cent over the year. On paper, the pipeline is working.

Completions tell a different story. In the June quarter, 44,328 dwellings were completed, up just 2.4 per cent. Delivering the national target of 1.2 million homes over five years requires an average of 60,000 completions every quarter. March completions sat around 26 per cent below that pace. The National Housing Supply and Affordability Council now expects the target will be reached at the end of 2030.

The direct relationship between approvals and commencement has weakened. A large volume of work is still to be done, and a high proportion of approved projects have yet to start.

Approval is permission to build. It is not proof that a project can be financed, sold or delivered. For developers, the question is now whether the numbers still work at the end of the build.

Residential values are also softening. Cotality’s national Home Value Index fell 1.2 per cent in October. Developers are positioned between costs to deliver and realisation on completion.

Social, affordable and first-home-buyer housing are often the first projects to be postponed when finance costs rise and values soften, with limited room for cost overruns and flexibility on price.

Softer activity should ease cost pressure and, in most cities, we expect escalation to moderate. But construction costs are cooling more slowly than the broader economy. Headline CPI eased to 3.8 per cent in the year to June, while home construction prices rose 5.9 per cent over the same period. Input prices for house building rose 2.1 per cent in the June quarter alone, the largest quarterly increase since 2022.

The cumulative picture is more revealing. Since 2019, timber costs are up about 44 per cent, other building inputs about 36 per cent and wages about 19 per cent. Construction company insolvencies have stayed above 3,000 a year for three consecutive financial years, after falling to a little under 1,000 in 2021.

Global shocks add to the pressure. Fuel surcharges have been switched on and off. New anti-dumping duties on Chinese steel and aluminum add a structural cost that will not reverse when oil prices do. Copper, pulled by demand from data centres, electrification and grid investment, is up more than 25 per cent year to date. Land costs have remained elevated. A developer can plan around a slow domestic cycle. A sudden commodity shock is much harder to absorb.

Where feasibility is the constraint, more approvals achieve little. There are, however, several ways government intervention could help improve project viability, including two potential approaches.

The first is direct delivery. Public building, through state housing agencies or partnerships with community housing providers, can bring forward supply where private feasibility has failed. Residential undersupply is a key factor in recovery, and government infrastructure investment is peaking in every state except Queensland. As the public construction workload eases, housing is the logical place for government effort to shift.

The second is targeted tax incentives for developers. Settings that reward completion rather than speculation would address the feasibility gap more directly. Concessions tied to delivery within a set period, or to designated cost rental housing developments that supply long-term, non-market-rate rental stock, would give developers a reason to build the product the market is least able to deliver.

Demand-side measures deserve the same scrutiny. Help-to-buy schemes appear to address affordability, but they mostly add pressure to the demand side of the equation. For first-home buyers using a 5 per cent deposit, there is higher potential for negative equity if values keep falling. Demand support can push prices up without adding a single home, so it should follow supply policy, not substitute for it.

Australia has plenty of projects on paper. The next task now is to turn them into homes. That means treating completions as the measure of success and recognising that the next phase of the housing debate is about delivery, not approvals.