Inland Rail has hit a major milestone, with all 12 Victorian enhancement sites between Beveridge and Albury (B2A) now ready for the operation of double-stacked freight trains.
Inland Rail Chief Executive Officer Dr Sean Sweeney said the milestone was an important moment for the project.
“The achievements on B2A come from a lot of hard work, consultation and cooperation with our contractors, stakeholders and local communities,” he said. “We thank the local communities along the B2A alignment for their patience and understanding as we push to finalise all major works before the end of the year.”
The Tallarook passing loop, the last of the key sites to achieve double-stack readiness, was commissioned and returned to service earlier this week after six months out of action.
Passing loops are parallel sections of track connected to a single-track rail line that allow trains to safely pass or overtake each other.
A 1.15km section of the loop was lowered by 2.1 metres under the Hume Freeway. The work involved removing 4,000 tonnes of material, replacing it with 4,000 tonnes of ballast and laying 1,650 new sleepers.
Inland Rail and construction partner John Holland are continuing station upgrades at Euroa and Benalla and completing the finishing works on bridges in Broadford and Wandong.
Work on the B2A Tranche 1 project began in March 2023 and included track lowering and bridge replacements at Barnawartha North, Glenrowan and Seymour Avenel Road, along with a railway station upgrade at Wangaratta.
The B2A Tranche 2 project began in June 2024 and is closing in on completion, with major bridge replacements or station upgrades at Wandong, Hume Freeway – Tallarook, Hume Freeway – Seymour, Broadford, Euroa and Benalla due to be completed before the end of the year.