Major piling for a new bridge on a closed section of a critical highway over the Blue Mountains has been completed on time, providing hope to motorists that a long disruption will eventually end.
More than eight months after the Great Western Highway was shut at Victoria Pass, contractors have finished driving 54 major piles – each up to 20 metres long – into bedrock for the new bridge structure over Mitchell’s Causeway.
It clears the way for the next step in construction of a reinforced concrete road deck above the stone causeway built by convicts nearly 200 years ago.
Renders of the final design that comprises an extra lane for eastbound vehicles navigating a steep ascent over Victoria Pass from the Central West have also been released. The third lane will sit on 14 piles that will be drilled into the ground and topped with 14 columns to support the new road deck.
The section of the state’s major east-west link has been shut since early March after engineers found serious cracking and ground movement in the stone causeway, which risked it collapsing.
The closure has forced up to 12,000 vehicles a day that had used the Great Western Highway to take detours.
The NSW government said the $200 million road project was on track for the highway at Victoria Pass to be reopened to two lanes of traffic between next April and June, while final construction timelines for the third lane will be determined after piling for it has progressed.
Since the highway was closed, motorists have had to use Darling Causeway and Chifley Road, a 25-minute detour. It has also placed financial pressure on business owners who relied on passing traffic at places such as Little Hartley in the Blue Mountains.
With a busy holiday period looming, Transport for NSW has advised those who have not driven the detour over the Blue Mountains to familiarise themselves with it.
“With the potential for extra traffic on the roads as people visit family or head on holidays, motorists should plan ahead, take it easy and show some patience to ensure everyone gets there and back safely,” the agency said.
Over the next six weeks, construction crews will also start work on the third lane by building a five-metre-high retaining wall. The safety work is needed to support a rig that will drive piles into the ground for the extra lane.
Once complete, motorists will have two eastbound lanes uphill for the entire 2.7-kilometre length of Victoria Pass from Little Hartley to Mount Victoria, enabling them to safely pass trucks and other slower vehicles.
NSW Roads Minister Jenny Aitchison said the work to initially restore two-way traffic on the highway at Victoria Pass was continuing to progress well, and the completion of the major piling was the project’s biggest milestone to date.
She acknowledged the ongoing disruption caused by the highway’s closure, thanking motorists for their patience and understanding.
Federal Transport and Infrastructure Minister Catherine King said the work to repair the highway was continuing at a rapid pace to restore full access through the Blue Mountains as quickly as possible.
The $200 million road project is jointly funded by the state and Commonwealth.
The state is also spending an extra $50 million on bolstering the detour routes , which has involved laying more than 50,000 tonnes of asphalt.