Olympic venues hit with new construction code as stadium dig hits 100th day

The Age •
November 18, 2026 • 03:43 AM
• By Cameron Atfield
2
2 reads 0 reactions

All 17 Brisbane 2032 venues will be bound by the state government’s strict new productivity rules after Jarrod Bleijie approved a retrospective rollout.

1 / 8
Swipe Photos

A new construction code introduced in response to the CFMEU inquiry will be retrospectively applied to Brisbane 2032 Olympic venues, Deputy Premier Jarrod Bleijie said on Wednesday as he marked 100 days of excavation at Victoria Park.

Speaking on the balcony of the former Victoria Park function centre, which now serves as a construction site office, Bleijie said the Games Independent Infrastructure and Coordination Authority (GIICA) had asked that the new code be applied to the 17 venues it will deliver.

The new productivity code, adopted by the Queensland government on Tuesday, sets mandatory workplace, safety, and industrial relations standards for publicly funded construction projects of $150 million and more.

“When [ Brisbane Stadium ] starts being constructed, it would have been under the old EB [enterprise bargaining] arrangements,” Bleijie said.

“That’s why we needed the code to apply. However, we did put a provision in the code that said it’s prospective – it’s going forward. But if line agency ministers or agencies wanted the code to apply to current tenders, they have to write to the responsible minister for approval.

“GIICA did that yesterday. By yesterday afternoon or last evening, I’d written back to GIICA and approved that.”

Included in the new code was a ban on unions forcing contractors to display flags and branding on sites.

“If you’re a new worker and you rock up and you are not a member of the CFMEU, the flags on the construction site are a sign you will not enter this construction site unless you are a member,” Bleijie said.

“And if they get there, they get bullied into joining the CFMEU. That’s not freedom of association.”

The CFMEU has already vowed to build the new Brisbane Stadium – for which construction was expected to begin by mid-2027 – due to its existing enterprise agreement with preferred builders BESIX Watpac and John Holland.

GIICA chair Stephen Conry said, in the first 100 days of the early works program at the Brisbane Stadium site, about 200,000 cubic metres of soil had been moved. About 65 workers had been at the site six days a week, weather permitting, to prepare the ground for the stadium’s construction.

“The cut-and-fill approach that we’ve adopted for the site has been very effective, very productive, and necessary when you look at the naturally hilly topography which surrounds us, and also to minimise traffic movements or truck movements from the site,” he said.

Conry said the project validation report for Victoria Park would be delivered in the first half of 2027, after which construction could commence.

Community consultation for the master planning for the site, being undertaken by Arup , has also concluded.

Arup Australia and New Zealand business director Penny Hall, who has headed the precinct master-planning process, said more than 42,000 people had logged in to the Victoria Park precinct website.

“They want to see better connections, better opportunity, vast open space, brilliant concerts, sporting events at all three of our major venues – the stadium, the National Aquatic Centre, and the RNA – and that’s exactly what we’re doing as we move forward,” she said.

Hall said the master plan was a “living document” and changes to the draft plan released in August were yet to be finalised.

“We’ve just started that process of consolidating all of the [public] comments and looking at how we’re embedding all of them into the update,” she said.

Bleijie said Exhibition Station would definitely be in use during the Games, despite International Olympic Committee concerns about its proximity to the planned athletes’ village within the RNA Showgrounds.

But pedestrian access to the site from the next-closest station, Fortitude Valley, from where many spectators would walk after pre-event food and drinks, remained an issue.

“Part of that’s really ensuring we’re creating exciting experiences for people as they arrive in that last mile to the whole precinct,” Hall said.

“We’re working with [Brisbane City Council] – they have their Fortitude Valley master plan – so we’re very much looking at all of that as the finalisation of this piece of work.”

You have reached your maximum number of saved items.

Remove items from your saved list to add more.

You've used all of your gift articles. 3 more will become available on the 1st of every month.

Prev Swipe Story Next

Same Story from Other Publications

Compare how 4 other independent news outlets reported on this story.

4 Publications
Sydney Morning Herald (SMH)
55m ago
Olympic venues hit with new construction code as stadium dig hits 100th day

Olympic venues hit with new construction code as stadium dig hits 100th day

All 17 Brisbane 2032 venues will be bound by the state government’s strict new productivity rules after Jarrod Bleijie approved a retrospective rollout.

#bleijie #brisbane #jarrod
Compare →
ABC News Australia
29m ago
Brisbane's Olympic stadium ahead of schedule but questions on costs swirl

Brisbane's Olympic stadium ahead of schedule but questions on costs swirl

The cost of early works for Brisbane's Olympic stadium remains hidden, while it has been revealed taxpayers will be slugged with the cost of the Gabba demolition.

#brisbane #victoria #olympic
Compare →
RealEstate.com.au News
1d ago
From stadium to housing: Inside the plan to reshape Woolloongabba - realestate.com.au

From stadium to housing: Inside the plan to reshape Woolloongabba - realestate.com.au

A new proposal puts thousands of homes, public spaces and an indoor arena on the cards for this inner-city Brisbane suburb.

#brisbane #stadium
Compare →
The Urban Developer
1d ago
CFMEU Inquiry Triggers Queensland Construction Code Overhaul

CFMEU Inquiry Triggers Queensland Construction Code Overhaul

New rules governing state-funded projects are now in force under reforms that have won praise from several quarters...

#construction #code
Compare →

Related Stories

Sports
Build #2612